Don’t you just love Yorkshire weather? After weeks where the ground could have held the house without piles, it’s been pouring down this week. And today was no exception - in more ways than one.


Today was the concrete pour into the piles.


I arrived at site about 9:45 and the truck with its boom arm was already in situ. Sensibly, the West Build team were sheltering in the van as the weather was slightly damp!


About 10:20 the mixer arrived and the fun began. It’s not pretty; it’s not skilful: it’s like very badly piping a birthday cake - at least like I’d do! Concrete (generally) went where it was supposed to but there was a lot of spillage. Some of this was scooped up to top up piles; a lot of it was left to become part of the wonderful mix of brick, cement bags and metal that we are going to live on.


Now onto the next stage...